5/9/2022
|
Payouts should have Been for previous load. These should be ignored..
|
|
5/9/2022
|
Live load.
Used Boat Form
|
|
5/10/2022
|
2 1/2 hours working on keel
|
|
5/10/2022
|
8 1/2 hours waiting on trailer repair.
3 hours working on keel.
|
|
5/11/2022
|
4 hours trying to reconfigure and get keel to stop moving.
|
|
5/12/2022
|
Lifted keel and placed more wood under it. Also figured how to get a chain on it. 4 hours working on it.
|
|
5/14/2022
|
Took all day to get boat, keel, mast, fin, and boom unloaded.
9am to 6pm
|
|
5/23/2022
|
Live load.
Sat 5/23/2022 from 1pm waiting on permits and route survey.
|
|
5/24/2022
|
Sat waiting on permits. All day.
|
|
5/25/2022
|
Waited on permits and state police. All day.
|
|
5/26/2022
|
Sat on side of the road waiting for permit.
2 hours.
|
|
5/26/2022
|
Down 1 hour due to high center.
|
|
5/27/2022
|
Had to shut down at 10a. No MD permit and no running after noon Friday.
|
|
5/28/2022
|
No movement allowed. Had to sit all day.
|
|
5/29/2022
|
No movement allowed. Sat all day.
|
|
5/30/2022
|
No movement allowed. Sat all day.
|
|
5/30/2022
|
Worked on truck and trailer lights for 3 hours.
|
|
5/31/2022
|
Could not leave until 9a. Permit restrictions.
|
|
6/17/2022
|
Live Load- 2 Masts 105 ft each
|
|
6/17/2022
|
Day Pay putting up mast rack- per Tim
|